Certificates

ASB/2026/47265

42 Fairmont Road, Cleethorpes · Fenland Safety Testing · officer Rachel Adeyemi

DeliveredDelivery: Downloaded

Certificate document

Source PDF received from the contractor

Electrical Installation Condition Report

BS 7671 · Requirements for Electrical Installations · 18th Edition

ASB/2026/47265

Page 1 of 6

Section A — Details of the client

ClientLincolnshire Housing Partnership
AddressMarsden House, Grimsby
UPRN100031018495

Section B — Installation address

Address42 Fairmont Road, Cleethorpes
PostcodeDN35 1JQ
OccupierPaula Osborne

Section C — Purpose of the report

PurposePeriodic inspection of the fixed electrical installation
Date of inspection15 Apr 2026
Records availableYes — previous EICR held on file

Section D — Summary of the condition of the installation

General conditionServiceable, no immediate danger identified
Overall assessmentUnsatisfactory
Next inspection recommended15 Apr 2031

Section E — Observations and recommendations

ItemObservationCode
1Bathroom supplementary bonding not verifiedC2
2No RCD protection on lighting circuitC3

Section F — Declaration

Inspected and tested byJ. Priestley
On behalf ofFenland Safety Testing
Scheme registrationNICEIC 0284/1187

Signature

Date

15 Apr 2026

This document is a demonstration facsimile generated for the LHP Compliance Portal preview.

Extracted information

Read automatically from the document

Property
42 Fairmont Road, Cleethorpes99%
Address
DN35 1JQ · UPRN 10003101849597%
Inspector
J. Priestley95%
Inspection date
15 Apr 202699%
Expiry date
15 Apr 203198%
Overall result
Unsatisfactory96%
Risk level
High93%

Observations

  • C2Bathroom supplementary bonding not verified
  • C3No RCD protection on lighting circuit

Quality assurance

Automated policy checks run against every incoming certificate before an officer decision.

No open findings
  1. Received
  2. Data Extracted
  3. QA Review
  4. Manager Approval
  5. Delivered

Extraction confidence

94.3%
All policy checks passed — no findings raised.

Delivery audit trail

Every step from receipt to tenant download, timestamped for auditing

  1. Certificate created

    Received from contractor portal · CERT-5065

  2. Data extracted

    18 fields extracted · property matched on UPRN

  3. Compliance Review completed

    Automated checks run against LHP electrical policy

  4. Approved by officer

    Rachel Adeyemi approved for delivery

  5. Email sent

    Delivered to Paula Osborne · certificate link + PDF attachment

  6. SMS sent

    Delivery notification sent to registered mobile

  7. Tenant viewed certificate

    Opened on mobile · Safari iOS

  8. Certificate downloaded

    PDF downloaded from tenant portal

  9. QR code scanned

    Scanned at property · consumer unit label