Consumer unit not of non-combustible construction
NC-4256 · C3 — Improvement recommended · raised 18 May 2026 against LGSR/2026/47615
Remedial workflow
Not a statutory breach; scheduled into planned works.
- Finding raised
- Logged with severity & owner
- Contractor notified
- Minor works scheduled
- Evidence submitted
- Reviewed
- Closed & linked
Issue detail
Plastic consumer unit installed under a previous regime. Improvement recommended at next planned upgrade.
- Discipline
- Gas
- Owner
- Morgan Lambert Ltd
- Contractor
- Morgan Lambert Ltd
- Target date
- 16 Aug 2026
- Days open
- 74 days
- Minor works order
- Not required for this code
Activity
Every note and decision, attributed and timestamped
Raised on site during inspection of 100 Bargate.
S. Baines · 18 May 2026, 00:00
Minor works order raised and appointment offered to the tenant.
Morgan Lambert Ltd · 19 May 2026, 00:00
Evidence reviewed and accepted. Issue closed and linked to the certificate.
Nadia Rahman · 20 May 2026, 00:00
Evidence
Photographs and completion notes held against the issue
Remedial photograph — after works
20 May 2026
Engineer completion note
20 May 2026
Recurrence
This property has repeated issues of this type. Flagged for pattern review and included in the Risk Dashboard.
Open Risk Dashboard