Non-Compliance Register

Consumer unit not of non-combustible construction

NC-4262 · C3 — Improvement recommended · raised 23 May 2026 against LGSR/2026/47517

C3Closed

Remedial workflow

Not a statutory breach; scheduled into planned works.

  1. Finding raised
  2. Logged with severity & owner
  3. Contractor notified
  4. Minor works scheduled
  5. Evidence submitted
  6. Reviewed
  7. Closed & linked

Issue detail

Plastic consumer unit installed under a previous regime. Improvement recommended at next planned upgrade.

Discipline
Gas
Owner
Trent Valley Inspections
Contractor
Grimsby Compliance Group
Target date
21 Aug 2026
Days open
69 days
Minor works order
Not required for this code

Activity

Every note and decision, attributed and timestamped

  • Raised on site during inspection of 31 Weelsby Street.

    L. Fairweather · 23 May 2026, 00:00

  • Minor works order raised and appointment offered to the tenant.

    Trent Valley Inspections · 24 May 2026, 00:00

  • Evidence reviewed and accepted. Issue closed and linked to the certificate.

    Nadia Rahman · 25 May 2026, 00:00

Evidence

Photographs and completion notes held against the issue

  • Remedial photograph — after works

    25 May 2026

  • Engineer completion note

    25 May 2026

Recurrence

No repeat pattern detected at this property for this issue type.

Open Risk Dashboard