Consumer unit not of non-combustible construction
NC-4268 · C3 — Improvement recommended · raised 19 May 2026 against LGSR/2026/47419
Remedial workflow
Not a statutory breach; scheduled into planned works.
- Finding raised
- Logged with severity & owner
- Contractor notified
- Minor works scheduled
- Evidence submitted
- Reviewed
- Closed & linked
Issue detail
Plastic consumer unit installed under a previous regime. Improvement recommended at next planned upgrade.
- Discipline
- Gas
- Owner
- Fenland Safety Testing
- Contractor
- Boston Electrical Partners
- Target date
- 17 Aug 2026
- Days open
- 73 days
- Minor works order
- Not required for this code
Activity
Every note and decision, attributed and timestamped
Raised on site during inspection of 52 Freeman Street.
M. Kowalski · 19 May 2026, 00:00
Minor works order raised and appointment offered to the tenant.
Fenland Safety Testing · 20 May 2026, 00:00
Evidence reviewed and accepted. Issue closed and linked to the certificate.
Nadia Rahman · 21 May 2026, 00:00
Evidence
Photographs and completion notes held against the issue
Remedial photograph — after works
21 May 2026
Engineer completion note
21 May 2026
Recurrence
This property has repeated issues of this type. Flagged for pattern review and included in the Risk Dashboard.